We are encouraged to see that the UK Government recognises that grid connection costs can be prohibitively high for developers. However, we are concerned by the decision to move more of the reinforcement costs to the network charges paid by “all electricity consumers in the area”.
We are encouraged to see that the UK Government recognises that grid connection costs can be prohibitively high for developers. However, we are concerned by the decision to move more of the reinforcement costs to the network charges paid by “all electricity consumers in the area”. Type: conclusion | Number: 13 | Paragraph: 76 | Response status: under_consideration Government response: As the Committee notes, from April 2023, Ofgem, has decided to socialise a further proportion of network reinforcement costs for distribution network connection customers. This will reduce the upfront cost. Part of the rationale for this change was to address the ‘chicken and egg’ issue referred to