However, HS2 Ltd’s latest cost estimate of £4.8 billion is significantly higher than previously reported, at £2.2 billion over the budget.49 The Department told us that it did not know of the £4.8 billion estimate until HS2 Ltd reported it to them during February and March 2023.50 Prior to that, the Department noted that HS2 Ltd had been reporting a cost estimate of £3.3 billion, within a range of £2.6 billion to £3.6 billion.51 It acknowledged that this cost pressure was ‘slightly greater’ t...
However, HS2 Ltd’s latest cost estimate of £4.8 billion is significantly higher than previously reported, at £2.2 billion over the budget.49 The Department told us that it did not know of the £4.8 billion estimate until HS2 Ltd reported it to them during February and March 2023.50 Prior to that, the Department noted that HS2 Ltd had been reporting a cost estimate of £3.3 billion, within a range of £2.6 billion to £3.6 billion.51 It acknowledged that this cost pressure was ‘slightly greater’ than the £0.4 billion being reported to Parliament but that those figures had not been validated while work was still underway.52 As a result, the Departm Type: conclusion | Number: 21 | Response status: accepted Government response: 5.1 The government agrees with the Committee’s recommendation. Target implementation date: December 2023 5.2 The HS2 Parliamentary report published in October 2022 set out HS2 Ltd.’s assessment of a £0.4 billion pressure for Euston station above its £2.6 billion budge