We concluded in our 2021 progress update on Crossrail that the Department had still not demonstrated that it is embedding lessons learned into its major programmes.62 When we asked the Department again about learning lessons, the Department and HS2 Ltd told us that they are learning from Crossrail, such as around programme and system integration and that there is a clear audit trail demonstrating how lessons have been applied.63 The Department also believed that the earlier identification of ...
We concluded in our 2021 progress update on Crossrail that the Department had still not demonstrated that it is embedding lessons learned into its major programmes.62 When we asked the Department again about learning lessons, the Department and HS2 Ltd told us that they are learning from Crossrail, such as around programme and system integration and that there is a clear audit trail demonstrating how lessons have been applied.63 The Department also believed that the earlier identification of problems at Euston compared to other rail programmes reflected how it is embedding learning into its projects.64 Type: conclusion | Number: 25 | Response status: not_addressed Government response: 6.1 The government agrees with the Committee’s recommendation. Target implementation date: Summer 2025 6.2 The department has a strong culture of learning lessons from managing major rail programmes, which includes working with the Infrastructure and Projects Authority in order to learn lessons from