In July 2023 we reported on how the Department’s previous plans for the HS2 station at Euston had proved to be unrealistic and unaffordable.42 Alongside the October 2023 cancellation of HS2 phases 2, the Department acknowledged that previous plans for the station had been unaffordable, and announced that the station design would be stripped back to focus on delivering a station that works and can be open as soon as possible. The Department announced that it “will deliver a new Euston Quarter ...
In July 2023 we reported on how the Department’s previous plans for the HS2 station at Euston had proved to be unrealistic and unaffordable.42 Alongside the October 2023 cancellation of HS2 phases 2, the Department acknowledged that previous plans for the station had been unaffordable, and announced that the station design would be stripped back to focus on delivering a station that works and can be open as soon as possible. The Department announced that it “will deliver a new Euston Quarter to provide much-needed homes”, appoint a development company (separate from HS2 Ltd) to manage delivery of the project, leverage private sector investmen Type: conclusion | Number: 21 | Response status: accepted Government response: 4.1 The government agrees with the Committee’s recommendation. Target implementation date: Summer 2024 4.2 The government’s ambition remains to make the best use of funding from alternative sources to enable the delivery of HS2 to Euston and the creation of a transfor