1. ORR welcomes the opportunity to contribute to the Public Bill Committee’s scrutiny of the
Railways Bill. This submission provides a summary of how the Bill and the establishment of
Great British Railways (GBR) is expected to affect the role of ORR.
2. The Bill will have a significant impact on ORR’s responsibilities, leading to a change in our
overall role. ORR will be undertaking a major transformation to fulfil its new role – including
as an independent, expert advisor to the Secretary of State – and to integrate with the wider
reform programme. This new role includes:
● A broader monitoring and reporting role covering all of GBR’s activities informed by
guidance from the Secretary of State, alongside a licence enforcement role that
includes long-term asset stewardship, GBR’s role in the management and operation of
industry retail systems, as well as requirements on passenger information, accessible
travel, complaints, delay compensation and the Rail Ombudsman;
● A reduced enforcement role in other areas, with a greater role for the Secretary of
State in holding GBR to account;
● A similar role to today for ORR in a new funding process with a wider scope centred
on advising funders on GBR’s integrated “track and train” business plan; and
● A reduced role for ORR in relation to access and use of the network, with GBR making
access decisions and setting access charges for use of the network, and ORR
performing a new appeals role.
3. There are also areas where ORR functions will not be impacted by the Bill, including health
and safety regulation, production of rail statistics, competition and consumer law
enforcement, and our existing roles in relation to roads, non-GBR infrastructure managers
and the Channel Tunnel. We will also continue to work closely with all operators,
infrastructure managers and stakeholders who will not be part of GBR.
4. This submission summarises the effect of the Bill on ORR’s role, structured in terms of:
(i) The Bill’s impact on what ORR does and how it does it;
(ii) Monitoring and enforcement;
(iii) The new funding process: the Funding Period Review;
(iv) Access and use of the network; and

(v) Next steps.
“ORR will play a central ongoing role in ensuring that the reformed rail system works
effectively. It will act as a critical friend to both the Department for Transport and
GBR – trusted to speak candidly, operate independently, and add value through
expertise.”
A Railway Fit for Britain’s Future: Government Response
The Bill’s impact on what ORR does and how it does it
5. ORR has a range of statutory functions which set out what it is expected to do. It also has
statutory duties which set out what it is expected to consider when carrying out its
functions, including when making decisions. ORR’s website provides an overview of its
current roles, including its current statutory duties and functions.
6. As a result of the Bill, ORR will have new and reformed functions including monitoring GBR’s
performance; enforcing GBR’s licence; advising funders as part of the new funding process
and determining appeals of GBR decisions on capacity allocation, access and charging. ORR
will no longer perform some of its existing roles, including in relation to track access,
passenger information, accessible travel, complaints, delay compensation and sponsorship
of the Rail Ombudsman. Further sections of this submission outline these changes in more
detail.
7. Many of ORR’s functions are not directly affected by the Bill, including:
● Health and safety: ORR will continue to regulate health and safety for the entire
mainline rail network in Britain, as well as London Underground, light rail, trams and
the heritage sector;
● Rail statistics: ORR will remain the primary producer of Official Statistics for rail, with
the majority of ORR statistics assessed and designated as National Statistics by the
Office for Statistics Regulation;
● Competition law: ORR will retain powers concurrent with the Competition and
Markets Authority (CMA) to enforce competition law in the sector, and to conduct
market studies where rail-related markets may not be functioning well (this is separate
from ORR’s duty to promote competition, which is outlined below);
● Consumer law: ORR will retain powers concurrent with the CMA to enforce consumer
law in the sector;

● Roads: ORR will continue to monitor and enforce the performance and efficiency of
National Highways, which manages the strategic road network in England;
● Other infrastructure managers: ORR will continue to regulate non-GBR rail networks
under the existing framework, for example High Speed 1, the Core Valley Lines and the
Crossrail Central Operating Section of the Elizabeth line;
● Channel Tunnel: ORR will retain functions relating to international train services
including economic and safety regulation of the Channel Tunnel; and
● Other roles: ORR will continue to perform other roles including train driver licensing;
interoperability authorisations; station, network and service closure ratifications and
regulatory functions in respect of Northern Ireland.
Statutory duties
8. The Bill provides ORR with reformed duties. These will replace ORR’s existing duties under
Section 4 of the Railways Act 1993 and will apply to all of our railway functions across GBR
and non-GBR – except for ORR’s health and safety, train driver licensing, competition and
consumer law functions (where ORR will continue to enforce competition and consumer law
concurrently with the Competition and Markets Authority).1
9. ORR’s reformed duties are aligned with those of Ministers and GBR and have a strengthened
focus on taking the public interest and public funding into account. These duties will define
how ORR will carry out its functions. In summary, they are to:
● Promote the present and future interests of passengers, including, in particular the
needs of disabled passengers;
● Promote the use of the railway for freight;
● Promote high standards of performance;
● Enable the industry to plan for the future with a reasonable level of assurance;
● Act in the public interest;
● Take the cost of public funding into account and the need to make efficient use of
public funding;
● Take safety into account in ORR’s non-safety functions;2
● Take any Secretary of State or Scottish Ministers’ guidance into account;3 and
● Take Secretary of State, Scottish Ministers’ and Welsh Ministers’ strategies into
account.4

10. These duties will set out what ORR must consider or aim to achieve when carrying out its
roles. While some of ORR’s duties in the Bill are the same as, or similar, to ORR’s current
duties, there are differences: for instance, ORR will no longer have specific duties relating to
the environment or sustainable development, but will have a new duty to act in the manner
best calculated to be in the public interest (which may include economic, social and
environmental considerations).
11. Depending on the circumstances, the changes to ORR’s duties could have a potential impact
on ORR’s policy approach in some areas or on individual decisions. As part of its
transformation under rail reform, ORR will consider in detail the exact impact of its reformed
duties on what it does and how it does it.
12. As today, ORR will also have a duty to promote competition – but this duty will not apply to
some ORR roles including regarding appeals on access and use of GBR’s network.5 This
means, for example, when deciding whether or not to uphold an appeal from an operator
who wants access to GBR's network, ORR will not consider how best to promote competition
in the provision of railway services for the benefit of users, as it does currently.
Monitoring and enforcement
Monitoring GBR’s statutory functions
13. At present, ORR monitors whether Network Rail is complying with requirements set out in its
network and station licences. In future, by contrast, ORR’s monitoring of GBR will be
primarily based on how GBR performs its statutory functions.6 Under the Bill, GBR’s
statutory functions which ORR must monitor include, in summary:7
● Managing, operating, maintaining, renewing and improving the network;
● Operating most railway passenger services in England, as well as cross-border services
in Scotland and Wales; and
● Setting fares, selling tickets, and providing essential systems and services to facilitate
the operation of railway passenger services.
14. This includes areas where ORR has not previously had a role, such as monitoring the
performance of passenger services. In performing its monitoring role, ORR will be informed
by guidance from the Secretary of State which will help to ensure that the monitoring is
targeted, proportionate and outcomes focused.
15. When monitoring GBR under the provisions of the Bill, ORR will consider whether and how
GBR is delivering the activities set out in its business plan. It will also consider the costs of
carrying out those activities, the income GBR has received, and how this compares to the

estimates presented in the business plan. ORR will also consider how GBR is helping to
further railway safety.
16. ORR will be able to investigate issues and raise them with GBR for attention. GBR is
ultimately accountable to the Secretary of State, so when exercising the monitoring role,
ORR will not have enforcement powers. ORR can instead raise issues with the Secretary of
State, who can decide whether to take further action.8 Scottish Ministers will also have
powers to act where Scottish railway activities are concerned.9
GBR licence
17. As well as monitoring GBR’s statutory functions, ORR will monitor and enforce GBR’s licence.
GBR’s licence will be drafted, issued and where necessary amended by the Secretary of
State.10 Development of GBR’s licence is currently underway, led by the Department for
Transport (DfT), and will be subject to public consultation. It is expected to be focused on
industry obligations and processes that GBR must fulfil or facilitate, and to include
requirements relating to passengers (see “Passenger Watchdog” below). Once issued, ORR
will also be able to modify GBR’s licence with GBR’s agreement.
18. In general terms, as is the case currently with Network Rail, if ORR suspects GBR may be in
breach of any of its licence conditions, ORR will be able to identify and investigate issues,
seek early resolution and take enforcement action if necessary. Unlike today, ORR will not be
able to issue a financial penalty for a GBR licence breach.11
19. GBR’s licence is expected to focus on a more targeted and specific range of activities than
the current Network Rail licence. The targeted nature of GBR’s licence means that ORR will
no longer be able to take enforcement action in some areas where it has done previously,
such as issuing enforcement orders in relation to train service performance. Instead, for
matters outside the scope of GBR’s licence, ORR would be able to investigate and raise
concerns to the Secretary of State via the statutory monitoring role outlined above. It would
then be for the Secretary of State to decide on any action.
20. Subject to consultation, the UK Government intends to include in GBR’s licence a narrow,
outcomes-focused requirement on long-term infrastructure asset stewardship. This will
ensure that ORR can take enforcement action which is effective and proportionate to the
long-term risk of asset deterioration. This is an important safeguard in how GBR looks after
its infrastructure in an efficient, sustainable way, while ensuring a safe and well-performing
railway.
21. In addition, GBR will be a retailer absorbing 14 current train operating companies’ ticket
retailing operations as well as owning and managing the central systems used by all retailers
– including its direct competitors. For this reason, GBR's licence will also contain a new

requirement to ensure GBR supports an open and competitive ticket retail market and treats
independent ticket-selling companies fairly.
22. GBR’s licence will require it to comply with a code of practice setting clear requirements for
how GBR will manage industry systems that facilitate the rail retail market, and how it must
interact with the rest of the market.12 The Secretary of State and ORR will jointly create the
code with input from industry and ORR will manage and enforce compliance with the code
via GBR’s licence. Non-GBR retailers will be able to challenge GBR decisions or actions they
consider to be non-compliant by raising them directly with ORR. ORR will be required to
investigate and, if it considers that GBR has not complied, it will be able to demand
corrective action by issuing binding orders on GBR.
Non-GBR licences
23. While GBR’s licence will be issued by the Secretary of State, ORR will continue to issue and
enforce railway licences for other operators and infrastructure managers across Great
Britain to ensure they are ‘fit and proper’ to run a railway and promote effective and
efficient working relationships across the sector. Non-GBR licence holders will include
devolved, freight, charter and passenger open access train operators; light maintenance
depot operators; some non-GBR infrastructure managers’ networks such as the Core Valley
Lines; and operators of over 800 stations that are expected to remain outside of GBR.
A new Passenger Watchdog
24. A new Passenger Watchdog will be established, grown out of Transport Focus. It is expected
to take on functions currently carried out by ORR in relation to passenger information,
accessible travel, complaints, delay compensation and sponsorship of the Rail Ombudsman.
The Passenger Watchdog will set requirements on industry in these areas through guidance
and codes of practice, subject to agreement by ORR and the Secretary of State.13 These will
be made binding on the industry via conditions in both GBR and non-GBR operators’
licences. The Passenger Watchdog is expected to monitor and publicly report on industry
performance against these standards, to seek improvements from industry, and may refer
concerns to ORR.14
25. ORR will continue to be responsible for enforcing the licence conditions associated with
these standards. This means it will be for ORR to decide whether to take enforcement action
in response to a potential licence breach, including following a referral from the Passenger
Watchdog. ORR will also retain its consumer law powers, which it has previously used in
areas such as improving the transparency of fees charged during the ticket buying process.
Key issues which matter to passengers, such as train service performance, will also be
encompassed in ORR’s wider roles monitoring GBR’s performance and providing advice to
funders on GBR's commitments in its integrated business plan.

Funding Period Reviewthe new funding process
26. Across all of its activities GBR will be funded from a range of sources including government
grants, income from fares, charges paid by non-GBR train operators for accessing GBR’s
network and property and commercial income. The Bill makes provision for a reformed five-
yearly funding process for GBR, known as the Funding Period Review (FPR).15 Unlike the
current periodic review, ORR will no longer conduct a review of charges paid by train
operators to access the network – as GBR will set charges under the new framework. ORR
will no longer make a final determination at the end of the process: instead, ORR will provide
advice to funders (Secretary of State and Scottish Ministers) throughout the process, and the
funders will approve GBR’s integrated business plan.
27. It is expected that the FPR will determine the funding for GBR’s network operation,
maintenance and renewals (OMR) activities – although the Bill allows for a wider range of
GBR activities to be funded via the new process if Ministers wish. In practice, this means that
although GBR’s assumptions about future passenger services funding and revenue will be
considered as part of GBR’s five-yearly business planning, to start with GBR’s passenger
services funding will be determined through the UK Government’s Spending Reviews,
separate from the new funding process.
How this will work
28. To a timeline to be defined by ORR, the Secretary of State will publish a Statement of
Objectives outlining the objectives for the railway (replacing today’s High Level Output
Specification, or HLOS), along with a Statement of Funds Available (SoFA) estimating the
funding the UK Government can provide to fund GBR (in addition to income from other
sources) in order to cover the expenditure required to deliver those objectives. The
Secretary of State will be required to consult ORR when developing the SoFA and a range of
parties – including devolved governments and authorities, ORR and the Passenger Watchdog
– when developing the Statement of Objectives.16
29. In response, GBR will develop an integrated business plan across all of its activities, based on
the objectives and funding estimates provided by the Secretary of State. While preparing the
business plan, GBR must consult a range of parties including the Secretary of State, ORR and
the Passenger Watchdog.17
30. ORR must assess GBR’s draft business plan and advise the Secretary of State on whether the
plan meets their objectives and whether the estimated costs offer good value for money.
ORR must also publish a summary of its advice. Following ORR advice, the Secretary of State
may approve the business plan. GBR must then provide ORR with the approved plan and
publish it.18 In Scotland, an equivalent process will apply.19

31. ORR expects the business plans to provide transparency about the activities GBR intends to
carry out during the five-year funding period. This is to enable the Secretary of State,
Scottish Ministers and ORR to monitor GBR’s performance against the plan and inform
funders’ final decisions.
32. Under the Bill, the Secretary of State and Scottish Ministers have the power to postpone,
withdraw or reduce financial assistance to GBR. If this variation is likely to have a material
impact on GBR’s ability to deliver the business plan, the Secretary of State or Scottish
Ministers must notify ORR and publish details of the variation.20 With the Secretary of State
or Scottish Ministers’ approval, GBR may amend the Integrated Business Plan in consultation
with ORR.21
Access and use of the network
The scale of non-GBR train operations and infrastructure
33. GBR will be formed out of Network Rail and will encompass the 14 train operating
companies currently contracted by DfT. GBR will operate the vast majority of rail
infrastructure, as well as most passenger services.
34. Nevertheless, based on the current distribution of services, non-GBR operators are expected
to remain significant users of the network, underlining the continued importance of ensuring
fair access to the network. In some parts of the network, most notably in Scotland and
Wales, GBR operated services will be in the minority. Around 40 entities who currently have
rights to use Network Rail’s network are expected to sit outside of GBR in the future model.
These include devolved passenger operators, freight and open access passenger operators,
and currently account for roughly:
● A quarter of train kilometres (primarily provided by the devolved operators in
Scotland, Wales, London and Merseyside);
● A third of passenger journeys (with nearly three quarters of these attributable to the
Elizabeth Line and London Overground);
● A fifth of the track access charges currently paid to Network Rail (primarily paid by
devolved operators, with freight operators paying 2% of access charges, and open
access passenger operators paying 1%); and
● 800 out of the approximately 2600 stations (the majority of which are operated by the
devolved operators owned by the Scottish and Welsh Governments).
35. The Bill allows Scottish Ministers and Welsh Ministers to arrange for GBR to operate
devolved train operating companies on their behalf – directly, via a subsidiary or via a jointly-

owned company. This means that the scale and nature of non-GBR services will depend on
whether the devolved governments make such arrangements.
Access, charging and appeals
36. The Bill makes significant changes to the legal framework for non-GBR operators seeking to
access the rail network. Under the framework:
● ORR will no longer approve or direct access contracts in advance for GBR, as ORR
currently does for Network Rail. Instead, GBR as the directing mind for rail
will determine access to its own network;22
● ORR will also no longer determine charges or the terms of train performance incentive
schemes: these will be set by GBR;23 and
● The Railways (Access, Management, and Licensing of Railway Undertakings)
Regulations 2016 (AMRs) will no longer apply to GBR. But ORR will continue to regulate
other UK infrastructure and facility managers under the AMRs which set the rules for
access to non-GBR infrastructure – meaning that the new access framework will apply
to GBR but not to other infrastructure managers.24
37. Under the Bill, GBR will be required to produce an Access and Use Policy (AUP) setting out
how it will make decisions regarding applications to use its network. GBR must consult ORR
on issuing or revising the AUP.25 GBR will also be required to produce an infrastructure
capacity plan, a working timetable, a charges scheme, and a performance scheme designed
to encourage GBR and operators to minimise disruption on the network.26
38. Under the Bill, provisions contained within these documents and schemes will be subject to
a new ORR appeals process, as will GBR’s specific decisions relating to access to
infrastructure, charging or performance schemes.27 ORR must evaluate appeals on the same
basis as a judicial review in England and Wales, or as an application to the supervisory
jurisdiction of the Court of Session in Scotland.28 This means that ORR must decide the
appeal on the basis of whether or not the GBR decision, policy or scheme has breached
public law principles – i.e. whether GBR has acted illegally, irrationally, not followed due
process or not honoured legitimate expectations.
39. If ORR upholds an appeal, it will have powers to quash GBR decisions, to order GBR to
reconsider and to give GBR directions about how it should reconsider (for example by
directing it to take a particular impact or statutory duty into account when it reconsiders its
decision). Alternatively, ORR may substitute its own decision for GBR’s – but only if GBR has
made an error of law and without that error there is only one decision that GBR could have
reached.29

40. The appeals mechanism in the Bill is therefore narrower than ORR’s current directing role
under the Railways Act 1993 and ORR’s current appeals role under regulation 32 of the
AMRs, in which – in the event of disagreement – ORR has broad scope to make decisions and
issue directions, so as to determine access and its terms, based on its judgement and
weighing its statutory duties.
41. Under the Bill, the Secretary of State will have powers to make regulations about the steps
which need to be taken before an appeal is made, to set fees and time limits for appeals and
to define how ORR is to carry out its appeals role. The Secretary of State must consult ORR
on any such regulations.30 Subject to any regulations, ORR will be responsible for developing
its own processes and decision criteria and will consult on this (see “next steps” below).
42. The UK Government intends ORR to report periodically on how the access regime is
facilitating private investment in rail, consistent with GBR’s duties and wider objectives set
by Ministers. ORR may also use its broad monitoring powers to consider and report on how
GBR manages the access and use of its network by third party operators.
43. Separate from the Bill, a new GBR network code will be created to replace the current
Network Code, the industry rules which set out how Network Rail and those who run trains
on its network must work together e.g. on timetabling. This will enable GBR to make
decisions about the content of the new code, replacing today’s system where changes
require broad industry consensus and ORR approval.
Next steps
44. ORR has initiated a transformation programme to create an organisation fit for the future
and is taking steps to adapt to its new role, promote the growth of the economy and support
the successful delivery of rail reform.
45. As train operating companies move into public ownership, ORR is also undertaking statutory
assessments of train operators’ Safety Management Systems (SMS), the formal framework
that sets out how they will meet their legal duties to manage their health and safety risks.
ORR will continue this work as more operators move into public ownership. ORR will
continue to engage with the relevant duty holders on the development and safety validation
of GBR's SMS, to make sure changes and their impacts on health and safety have been
appropriately assessed and addressed to ensure and enable a safe and effective transition.
46. ORR has also worked at pace to ensure that newly publicly owned operators hold the
appropriate licences and access contracts. We will carry on with this important work to
ensure continuity of train services as the remaining DfT operators transition into public
ownership.

47. In parallel with the passage of the Bill, ORR will continue to work with DfT, Transport
Scotland, Welsh Government, Mayoral Combined and Strategic Authorities, Network Rail,
Transport Focus and all relevant stakeholders on non-legislative aspects of the reform
programme:
● The Bill’s impact on what ORR does and how it does it: ORR will develop its new
policy approach to its role under the new framework, including its new and reformed
functions and duties. ORR will consult on relevant aspects of its approach.
● Monitoring and enforcement: ORR will:
– engage with DfT as GBR’s licence is developed, alongside developing its new policy
approach to monitoring GBR and making relevant changes to non-GBR licences;
– work with DfT, the Rail Delivery Group and retailers to develop proposals for the
new retail management arrangements and code of practice that provides robust
safeguards to ensure that GBR acts impartially in overseeing the retail market;
– collaborate with DfT and Transport Focus to establish the necessary arrangements
for the Passenger Watchdog to be ready to exercise its new powers and functions at
the point of GBR stand-up, including a Memorandum of Understanding to ensure
effective coordination and transparency in how ORR and the Passenger Watchdog
will work together under the new framework; and
– work with DfT, the Passenger Watchdog and non-GBR operators to achieve
consistency between their own licence requirements and the requirements on GBR.
● New funding process: ORR will work with funders, Network Rail and subsequently GBR
on a smooth transition into the five-year funding period to ensure continuity of
funding for GBR and the supply chain.
48. Access and use of the network: Network Rail has published a discussion document on GBR’s
AUP. ORR will continue to work with Network Rail as it develops the AUP and engages with
stakeholders including supporting Network Rail in developing its approach to assessing the
economic effects of proposed open access services. ORR is currently developing its policy
approach to its new appeals role and recently published a discussion document to provide
an early opportunity for industry to comment on how ORR plans to carry out its new role.

1 The new duties include those set out in the Railways Bill at cl 18, cl 19 and cl 20
2 Railways Bill cl 19
3 Railways Bill cl 21 and cl 22
4 Railways Bill cl 16(2)
5 Railways Bill cl 20
6 Railways Bill cl 74(2), which inserts a new section 69A into the Railways Act 1993
7 GBR’s functions include those set out in the Railways Bill cl 3(1)
8 Railways Bill cl 7, cl 9 and cl 74(2)
9 Railways Bill cl 8 and cl 10
10 Railways Bill Schedule 1, para 3, which substitutes section 8 in the Railways Act 1993.
11 Railways Bill cl 75(3)
12 Railways Bill Schedule 1, para 5, which inserts a new section 9A into the Railways Act 1993
13 Railways Bill cl 46
14 Railways Bill cl 42, cl 43, cl 46 and cl 47
15 Railways Bill, Schedule 2, Part 1, para 1 and Part 2 para 8
16 Railways Bill, Schedule 2, Part 1, para 2 and para 3
17 Railways Bill, Schedule 2, Part 1, para 4
18 Railways Bill, Schedule 2, Part 1, para 4
19 Railways Bill, Schedule 2 Part 2
20 Railways Bill, Schedule 2, Part 1, para 7 and Schedule 2, Part 2, para 14
21 Railways Bill, Schedule 2 5 (2) and Schedule 2 12 (2) (a)
22 Railways Bill, cl 69 and cl 70
23 Railways Bill, cl 13 (1)
24 Railways Bill, cl 72 (2)
25 Railways Bill, cl 59 and cl 66
26 Railways Bill, cl 60, cl 61, cl 62, cl 64 and cl 65
27 Railways Bill, cl 59(6), cl 60(6), cl 61(5), cl 62(7), cl 64(8), cl 65(7), cl 67
28 Railways Bill, cl 68
29 Railways Bill, cl 68(4)(b)
30 Railways Bill, cl 68(6) and (7)